West King Street (County Road 214) Resurfacing from County Road 13 to Palmer AvenueAffected Areas
Roads: County Road 13, County Road 214 Counties: St. Johns Cities: Green Cove Springs Overview
Project Began: April 2010 Expected Completion: Summer 2010 Project Description
Resurfacing from County Road 13 to Palmer Avenue (14.7 miles) and paving shoulders from County Road 13 to County Road 13A (4 miles). Halifax Paving of South Daytona began April 5, 2010 and should finish in 120 days (Summer of 2010) at a cost of $1,128,000. This is a federal economic stimulus project. Tom Thursby of Volkert Construction Services is CEI project manager (813-875-1365). Donnie Devenny/FDOT project manager. (4262141, 4263351, 4263341) For More Information Contact: |