West King Street (County Road 214) Resurfacing from County Road 13 to Palmer Avenue

Affected Areas
Roads: County Road 13, County Road 214
Counties: St. Johns
Cities: Green Cove Springs
Overview
Project Began: April 2010
Expected Completion: Summer 2010
Project Description

Resurfacing from County Road 13 to Palmer Avenue (14.7 miles) and paving shoulders from County Road 13 to County Road 13A (4 miles). Halifax Paving of South Daytona began April 5, 2010 and should finish in 120 days (Summer of 2010) at a cost of $1,128,000. This is a federal economic stimulus project. Tom Thursby of Volkert Construction Services is CEI project manager (813-875-1365). Donnie Devenny/FDOT project manager. (4262141, 4263351, 4263341)


For More Information Contact:
Gina Busscher - 800-749-2967
gina.busscher@dot.state.fl.us