Heckscher Drive (State Road 105) Resurfacing from New Berlin Road to Blount Island Drive

Affected Areas
Roads: State Road 105
Counties: Duval
Cities: Jacksonville, Mayport
Overview
Project Began: March 2010
Expected Completion: Summer 2010
Project Description

Resurfacing from New Berlin Road to Blount Island Drive (1.1 miles). Duval Asphalt Products Inc., of Jacksonville began March 25, 2010 and should finish in 75 days (Summer of 2010) at a cost of $775,220. Ted Rice/project manager. (2093365)


For More Information Contact:
Mike Goldman - 800-207-8236
michael.goldman@dot.state.fl.us