Heckscher Drive (State Road 105) Repaint Bridge over Sisters CreekAffected Areas
Roads: State Road 105 Counties: Duval Cities: Jacksonville Overview
Project Began: March 2010 Expected Completion: Fall 2011 Project Description
Repainting bridge over Sisters Creek. Kiewit Southern Company started March 1, 2010 and should finish in 510 days (Fall of 2011) at a cost of $3,195,083.51. Kregg Diemer of Parsons Transportation Group (904-596-1417) is CEI project manager. Kenny Geisendorff/FDOT project manager. (2096074) For More Information Contact: |