Butler Boulevard (S.R. 202) Lane Addition and Resurfacing from east of Kernan Blvd to San Pablo RoadAffected Areas
Roads: State Road 202 Counties: Duval Cities: Jacksonville Overview
Project Began: July 2007 Expected Completion: Early 2010 Project Description
Adding two lanes and resurfacing from east of Kernan Boulevard to San Pablo Road (5.8 miles). J.B. Coxwell Contracting Company of Jacksonville began July 9, 2007 and should finish in 878 days (Early 2010) at a cost of $30,610,326.65. John Kemp of Parsons Brinckerhoff is CEI project manager (904-645-3559). Jessica Tippet/FDOT project manager. (2097334) For More Information Contact: |