Butler Boulevard (S.R. 202) Lane Addition and Resurfacing from east of Kernan Blvd to San Pablo Road

Affected Areas
Roads: State Road 202
Counties: Duval
Cities: Jacksonville
Overview
Project Began: July 2007
Expected Completion: Early 2010
Project Description

Adding two lanes and resurfacing from east of Kernan Boulevard to San Pablo Road (5.8 miles). J.B. Coxwell Contracting Company of Jacksonville began July 9, 2007 and should finish in 878 days (Early 2010) at a cost of $30,610,326.65. John Kemp of Parsons Brinckerhoff is CEI project manager (904-645-3559). Jessica Tippet/FDOT project manager. (2097334)


For More Information Contact:
Mike Goldman - 800-207-8236
michael.goldman@dot.state.fl.us